The Clubhouse changes are starting to take shape, with walling in place and first fix electrics due for completion by the end of February. The work already undertaken does more than hint at the improvement, with the additional space and double aspect bar increasing the utility of the overall space significantly and new lighting brightening the place up no end. We thought you might like to know the schedule for remaining works:

Decorations: week commencing March 4th (duration 3.5 to 4 weeks)

Carpets: Late March/early April (duration 5-8 days)

Furniture: first week in May

Curtains: April/May

Second fix electrics

By the time this is all done the course changes will be bedding in nicely, the combined works making us all extremely excited about the overall KGC experience this year.

 