A week in the life of greens (19-23 Nov 2018)

The planned schedule of works for this week included;

Contractor verti spiking fairways.

Sand removal from fairway bunkers on the 6th.

Leaf removal!.

Tree felling.

General day to day course maintenance.

Monday

Swished greens.Bunkers raked. Tee markers moved.

Blue lining completed.

Leaf blowing, collection and mulching.

Hullah's on site verti spiking 8th fairway

image

This work was on-going all week.

Tuesday

Swished and removed debris from the greens.

Tee markers moved

Sand removed from both approach bunkers on the 6th in preparation for renovation work to be done.

Five trees felled on the right side of the 18th.

Rest of day devoted to leaves.

Wednesday

Course inspection carried out.

Usual green attention along with removing water from those greens that were flooded.

Repairs carried out to 9th and 16th bunkers following animal damage.

Machinery set up for planned vertical spiking of greens and tees.

Verti spiking attachment

Verti spiking attachment

Thursday

Course inspection at first light.

Greens swished and debris removed.

Bunkers had leaves removed and were then raked.

Ransome gang cutting units(all 5 cylinders) were stripped down for major overhaul.

Jake painting one of the cylinders

Jake painting one of the cylinders

Gang units fully stripped down

Gang units fully stripped down

Friday

Weekend preparations started for the up-coming Saturday and Sunday competitions.

All greens and approaches cut.

bunkers raked  and tee markers moved.

Leaf blowing,collecting and mulching for the remainder .

Fairway verti spiking completed by contractor.

 

 

Posted in .